Technology International Incorporated 0f Virginia
US Department of Energy

Conceptual Fusion Reactor Design and System Studies of the Reversed-Field Pinch

CUSTOMER: Los Alamos National Laboratory, Los Alamos, NM

CONTRACT #: 9-X62-9197K-1

STARTING DATE: May 1981                       

DURATION: 30 months

AMOUNT: $190,835

PRINCIPAL INVESTIGATOR: Dr. Randy Hagenson

TECHNICAL MONITOR: Dr. Robert Krokowski, LANL

 

 

 

Parameter Identification Technique, A New Approach to Wear Measurement in LMFBR

CUSTOMER:  U.S. Department of Energy (DOE), German Town, MD and Oak Ridge,

 TN

SUBCONTRACTOR: Argonne National Laboratory, West, Idaho Falls, ID

Subcontractor Team: Ronald W. King and Reed Manson

CONTRACT #: DOE-05-84ER80121.000

STARTING DATE: 9-13-84

DURATION:30 months

AMOUNT: $549,932

PRINCIPAL INVESTIGATOR: Dr. Shahla Keyvan

OTHER KEY PERSONNEL: Richard E. Jarka - Dr. Abdo A. Husseiny - Pamela Hoeppel - Dr. Neerchal K. Nagaraj - Dr. Enju Liang

TECHNICAL MONITOR:      Andrew Van Echo, DOE

 

 

A Compact Electrodialysis-Freezing, Low-Level Radioactive Waste Volume Reduction System for Nuclear Power Plants

CUSTOMER:  U.S. Department of Energy, German Town, MD

CONTRACT #: DE-AC05-84ER80199

STARTING DATE: September 1984  

DURATION: 6 months

AMOUNT: $50,000

PRINCIPAL INVESTIGATOR: Dr. Abdo A. Husseiny

TECHNICAL MONITOR: EG&G, Idaho Falls, ID

 

 

A Reliable Fuzzy Fault-Tolerant Controller 

CUSTOMER: U.S.  Department of Energy, German Town, MD

CONTRACT #: DE-AC05-87ER80509

STARTING DATE: June 1987

DURATION: 6 months

AMOUNT: $49,970

PRINCIPAL INVESTIGATOR: Rodrigo J. Rodriguez

OTHER KEY PERSONNEL: Dr. Abdo A. Husseiny - Dr. Zeinab A. Sabri - Dr. Neerchal K. Nagaraj - Dr. Enju Liang - Richard E. Jarka

TECHNICAL MONITOR: Harry Alter, DOE